Project Duration
Stipulated Date of Commencement
July 26 2019
Stipulated Date of Completion /
Likely Date of Completion August 04 2020
Likely Date of Completion August 04 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,272,856.00
Awarded for
₹ 18,221,892.83
Project highlights
Repair/Upgrdation works of schools which includes roofing , tiling,dadoes, painting, etc.
Contractors
M/s. Saad Infrastructure India Pvt. Ltd
Consultants
M/s. Bhaskar Wagle and Associates.