Project Duration
Stipulated Date of Commencement
July 26 2019
Stipulated Date of Completion /
Likely Date of Completion August 04 2020
Likely Date of Completion August 04 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,272,856.00
Awarded for
₹ 18,221,892.83
Project highlights
Repair/Upgrdation works of schools which includes roofing , tiling,dadoes, painting, etc.
Contractors
M/s. Saad Infrastructure India Pvt. Ltd
Consultants
M/s. Bhaskar Wagle and Associates.
See Similar Projects
Construction of Ashram school under Centrally sponsored scheme of Ministry of Tribal affaires at Moshiphond in the Village Ponguinim of Canacona Taluka.
View Project
Repairs/ Upgradation & Maintaince of Government schools in the State of Goa – Civil, Plumbing & Electrical Woks – Canacona Package-II (GPS Baddem, GPS Avali, GPS Dabel, GHS Shristhal in Canacona Taluka)
View Project
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa: Package -I (GPS Yeda, GPS Kuskem, GPS Barse, GPS Mahalbadem in Canacona Taluka
View Project