Project Duration
Stipulated Date of Commencement
February 13 2019
Stipulated Date of Completion /
Likely Date of Completion October 28 2019
Likely Date of Completion October 28 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,586,617.00
Awarded for
₹ 11,838,449.94
Contractors
M/s. Crystal Ball
Consultants
M/s. Bhaskar Wagle and Associates.