Project Duration
Stipulated Date of Commencement May 03 2018
Stipulated Date of Completion /
Likely Date of Completion
March 16 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 18,154,203.78
Awarded for ₹ 18,722,224.15

Project highlights

Repairs/Upgradation & maintenance of Government Schools

 
Gallery Image
Contractors
M/s. K. G. Thomas
Gallery Image
Consultants
M/s. Creative Abode
 
Similar Projects

See Similar Projects

Similar Project

Desks & chairs for Govt. schools / colleges.

View Project
Similar Project

Construction of National Institute of Water Sports Campus at Caranzalem, Goa – Balance – Civil, Plumbing, Electrical, Fire Fighting and HVAC works

View Project
Similar Project

Furnishing Work of Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.