Project Duration
Stipulated Date of Commencement
April 23 2014
Stipulated Date of Completion /
Likely Date of Completion June 06 2014
Likely Date of Completion June 06 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,999,658.00
Awarded for
₹ 4,999,658.00
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s.S M Realtors
Consultants
M/s.Creative Abode
See Similar Projects
Repairs/ Upgradation & Maintainence of Government schools in the State of Goa – Pernem Taluka – Package II (GPMS Pernem, Office of the ADEI Pernem)
View Project
Furniture work.
View Project
Repairs, Upgradation & Maintenance of Government Schools in the State of Goa – Packge O (Sattari Taluka) – (GPS, Gaonkarwada Vantem, GPS Vantem, GPS Advoi)
View Project





