Project Duration
Stipulated Date of Commencement
January 11 2019
Stipulated Date of Completion /
Likely Date of Completion September 26 2019
Likely Date of Completion September 26 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,329,014.00
Awarded for
₹ 14,368,822.70
Project highlights
Repairs/Upgradation and maintenance of Government schools in the state of Goa – Sattari Taluka
Contractors
M/s. Crystal Ball
Consultants
M/s. Bhaskar Wagle and Associates