Project Duration
Stipulated Date of Commencement
June 16 2016
Stipulated Date of Completion /
Likely Date of Completion August 15 2016
Likely Date of Completion August 15 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,671,788.00
Awarded for
₹ 9,293,791.89
Project highlights
The work involves repairs of roofing, false ceiling, painting, etc.
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Bhaskar Wagle and Associates
See Similar Projects
Renovation/Maintenance of Hospitals, CHCs, PHCs, and RMDs under Directorate of Health Services in North Goa –S.H : Maintenance/Renovation work of Community Health Centre at Bicholim – AMC for 200kVA Transformer at CHC Bicholim for 3 years (2019-2022).
View Project
Civil,Plumbing,Electrical,Fire fighting, Lift and HVAC works.
View Project
SITC of medical gas supply system (MGSS)
View Project





