Project Duration
Stipulated Date of Commencement
April 18 2022
Stipulated Date of Completion /
Likely Date of Completion August 30 2024
Likely Date of Completion August 30 2024
Status
30%
Completed
Cost (₹)
Estimated at
₹ 11,680,980.00
Awarded for
₹ 12,055,767.00
Project highlights
The scope of work includes construction of Concrete road, laying of pavers, etc.
Contractors
M/s. A.R. Constructions
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd