Project Duration
Stipulated Date of Commencement
April 18 2022
Stipulated Date of Completion /
Likely Date of Completion August 30 2024
Likely Date of Completion August 30 2024
Status
30%
Completed
Cost (₹)
Estimated at
₹ 11,680,980.00
Awarded for
₹ 12,055,767.00
Project highlights
The scope of work includes construction of Concrete road, laying of pavers, etc.
Contractors
M/s. A.R. Constructions
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd
See Similar Projects
Upgradation of Infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme 2013 – Construction of Multipurpose Sports Complex (Institutional Buildings) in SY.No.233/1 of Verem-Vagurme, Ponda Taluka.
View Project
Re-Construction of existing building of Village Panchayat to accommodate Market Complex and Multipurpose Hall at Village Panchayat Sancordem
View Project
Upgradation of infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme :
View Project