Project Duration
Stipulated Date of Commencement March 06 2024
Stipulated Date of Completion /
Likely Date of Completion
August 30 2024
Status
20%
Completed
Cost (₹)
Estimated at ₹ 18,534,545.98
Awarded for ₹ 26,275,688.00

Project highlights

The scope of work includes Acoustic Wall panaelling, Acoustic False ceiling, signages, Furniture works, aluminium louvers, etc.

 
Gallery Image
Contractors
M/s. Deshpande Constructions
Gallery Image
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd
 
Similar Projects

See Similar Projects

Similar Project

Reconstruction of Panchayat Ghar along with commercial shops, hall and other amenities for administrative purpose at Molcornem, Quepem, Goa.

View Project
Similar Project

Re-Construction of existing building of Village Panchayat to accommodate Market Complex and Multipurpose Hall at Village Panchayat Sancordem

View Project
Similar Project

Upgradation of Infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme 2013 – Construction of Multipurpose Sports Complex (Institutional Buildings) in SY.No.233/1 of Verem-Vagurme, Ponda Taluka.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.