Project Duration
Stipulated Date of Commencement August 10 2010
Actual Date of Completion May 30 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,852,975.00
Awarded for ₹ 4,026,350.00
Final Cost of Project ₹ 4,026,350.00
 
Contractors
M/s ThyssenKrupp (I) Pvt Ltd
Consultants
M/s. Effective Architectural Services
 