Project Duration
Stipulated Date of Commencement November 13 2010
Actual Date of Completion October 06 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 14,016,915.00
Awarded for ₹ 11,962,654.36
Final Cost of Project ₹ 10,494,521.06
 
Contractors
M/s Sunshine Electric Co. Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
 