Project Duration
Stipulated Date of Commencement June 15 2011
Stipulated Date of Completion /
Likely Date of Completion
October 14 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,609,226.00
Awarded for ₹ 6,841,664.00
 
Gallery Image
Contractors
M/s. Power & Instrumentation (Guj) Ltd.
Gallery Image
Consultants
M/s. Keni & D’Souza
 
Similar Projects

See Similar Projects

Similar Project

Supply, Installation, Testing and Commissioning of Echo machines.

View Project
Similar Project

Extension of R.M.Os Hostel at Goa Medical College and Hospital, Bambolim, Goa – Sewage Treatment Plant

View Project
Similar Project

Supply, Testing and Commissioning of OT Table with Accessories

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.