Project Duration
Stipulated Date of Commencement
September 14 2010
Stipulated Date of Completion /
Likely Date of Completion September 13 2011
Likely Date of Completion September 13 2011
Status
Completed
Cost (₹)
Estimated at
₹ 97,704,352.00
Awarded for
₹ 96,298,092.54
Project highlights
Renovation/Refurbishment of existng building
Contractors
M/s. D. S. Contractors Private Limited
Consultants
M/s. Effective Architectural Services