Project Duration
Stipulated Date of Commencement
May 29 2015
Stipulated Date of Completion /
Likely Date of Completion August 28 2015
Likely Date of Completion August 28 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 13,635,824.00
Awarded for
₹ 12,954,011.47
Project highlights
• Total built-up area : 400 sq. m.
• Conference Room.
• Director and Deputy Director’s Cabin.
• Work Stations for Staff.
• Server Room
Contractors
M/s. Vector Projects India Pvt. Ltd.
Consultants
M/s. Nilesh Salkar Associates