Project Duration
Stipulated Date of Commencement November 06 2019
Actual Date of Completion September 30 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,361,697.34
Awarded for ₹ 3,014,078.00
Final Cost of Project ₹ 3,014,078.00
 
Contractors
M/s. Raveena Watertech
Consultants
In House
 