Project Duration
Stipulated Date of Commencement
November 06 2019
Stipulated Date of Completion /
Likely Date of Completion October 09 2019
Likely Date of Completion October 09 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,361,697.34
Awarded for
₹ 3,014,078.00
Contractors
M/s. Raveena Watertech
Consultants
In-house (GSIDC)