Project Duration
Stipulated Date of Commencement
March 08 2019
Stipulated Date of Completion /
Likely Date of Completion May 07 2019
Likely Date of Completion May 07 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,305,526.00
Awarded for
₹ 4,299,500.00
Project highlights
Supply, Installation, Testing & Commissioning of 500KVA DG set
Contractors
M/S. Power Engineering (India) Pvt Ltd
Consultants
In-house (GSIDC)
See Similar Projects
Civil, Plumbing, Electrical, Lift & Fire – Fighting works
View Project
Maintenance work at Goa Medical College & Hospital and Health Centre’s under the jurisdiction of GMC, Bambolim, Goa- Exterior & Interior Painting Works
View Project
Lift work.
View Project