Project Duration
Stipulated Date of Commencement November 20 2019
Actual Date of Completion November 19 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,612,007.00
Awarded for ₹ 2,612,007.00

Project highlights

AMC of chiller

 
Contractors
M/s Carrier Air Conditioning & Refrigeration Ltd
Consultants
INHOUSE
 