Project Duration
Stipulated Date of Commencement October 30 2013
Actual Date of Completion November 18 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 9,800,679.00
Awarded for ₹ 12,439,387.00
Final Cost of Project ₹ 10,342,080.00

Project highlights

Refurbishment work of Maquiniz Palace complex prior to IFFI 2013.

 
Contractors
M/s. H. Candolcar & Sons
Consultants
M/s. UCJ Architecture & Environment
 