Project Duration
Stipulated Date of Commencement
October 30 2013
Actual Date of Completion
November 18 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,800,679.00
Awarded for
₹ 12,439,387.00
Final Cost of Project
₹ 10,342,080.00
Project highlights
Refurbishment work of Maquiniz Palace complex prior to IFFI 2013.
Contractors
M/s. H. Candolcar & Sons
Consultants
M/s. UCJ Architecture & Environment