Project Duration
Stipulated Date of Commencement October 01 2013
Actual Date of Completion January 15 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 12,326,816.00
Awarded for ₹ 10,499,999.00
Final Cost of Project ₹ 16,480,433.00

Project highlights

The scope of work involves dismantling of the existing nonfunctional VRV System and installation of the new VRV Air-Conditioning System at Maquinez Palace and Maquinez Palace Annex Building.

 
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
M/s. UCJ Architecture & Environment
 