Project Duration
Stipulated Date of Commencement
October 21 2014
Stipulated Date of Completion /
Likely Date of Completion December 03 2014
Likely Date of Completion December 03 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 73,22,326
Awarded for
₹ 71,38,872.7
Project highlights
Interior repairs works at Chairmans office at Maquinez Palace.
Contractors
M/s. Concept Creators
Consultants
M/s. UCJ Architecture & Environment