Project Duration
Stipulated Date of Commencement January 20 2011
Actual Date of Completion March 20 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 40,22,007.00
Awarded for ₹ 38,60,325.00
 
Contractors
M/s. Hitech Engineering Works
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 