Project Duration
Stipulated Date of Commencement
June 16 2011
Actual Date of Completion
March 25 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,57,17,757.00
Awarded for
₹ 23,604,023.00
Contractors
M/s. Manguirish Air Conditioning Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.