Project highlights
The primary health centre is situated at the prime location and caters population of Sanquelim and neighboring areas. It is situated near the old Primary Health Centre, at the junction of Bicholim to Valpoi road and Amona to Sanquelim road and about 1 Km away from the Sanquelim Market / Kadamba Bus Stand. The building is designed in “Y” shape by which it provides adequate light and ventilation to the entire area of hospital. All the three wings connecting to the central location serves as full functional area keeping the entire hospital services nearby and centrally located corridors to facilitate functional working of the hospital. The said building is 70 bedded hospital with RCC framed structure having partly second floor with sloping roof slab over one full first floor and over a ground floor without any basement.
The ground floor consists of N.G.O., immunization, pediatric physiotherapy councilor’s stimulation, pediatric clinic, play area, breast feeding, waiting area, obsterics & gyn, behavioral science, store room, gents and ladies toilet, M.S. room, medical store, surgical examination, pharmacy, treatment room, medical exam, herb room, sterile store, autoclave, ayurved / homeopathy, canteen, kitchen, utilities / maintenance, laundry, housekeeping, dental, opth/ENT, Administration, sample collection, laboratory, ortho, physiotheraphy, X-Ray, Ultra sound, trauma OT, Doctor’s room, trauma ward, etc.
The first floor consists of male ward, female ward, medical ICU, treatment room, gents and ladies toilet, Doctor’s room, neo-natal ICU, dialysis / Urology, two operation theatres, recovery room, sterile store, doctor’s / nurses’ changing room, delivery room, labour room, sluice, scrub, etc.
The second floor consists of seminar room, nurses’ rest room, doctor’s rest room, study room, bed room / living area, kitchen with attached toilet for DNB students (2 Nos.), 2 Nos. paid ward.
Other structures such as guard house, substation, mortuary, gas manifold, etc. are provided within the hospital campus.
Contractors
Consultants
Sub Works
This project involved 13 sub works. The details of the same available below
External Electrical works
Likely Date of Completion April 02 2012
Contractors
Consultants
Air conditioning works
Likely Date of Completion April 02 2012
Contractors
Consultants
Lift work
Likely Date of Completion March 02 2012
Contractors
Consultants
Steel Operation Theatre work.
Likely Date of Completion March 30 2012
Contractors
Consultants
Medical gas and Vacuum System work
Likely Date of Completion March 20 2012
Contractors
Consultants
Interior and Furniture works
Likely Date of Completion April 20 2012
Contractors
Consultants
Mortuary cabinet work
Likely Date of Completion December 20 2011
Contractors
Consultants
Internal Electrical works
Likely Date of Completion March 31 2012
Contractors
Consultants
Fire fighting, fire alarm and PA System works
Likely Date of Completion January 24 2013
Contractors
Consultants
Interiors (Loose Furniture Works)
Likely Date of Completion August 20 2012
Contractors
Consultants
Interiors (Loose Furniture Works)
Likely Date of Completion August 20 2012
Contractors
Consultants
Landscaping works
Likely Date of Completion August 14 2012
Contractors
Consultants
Compound wall work.
Likely Date of Completion January 20 2014
Contractors
Consultants
See Similar Projects
sewage treatment plant at 30 KLD capacity
View ProjectSupply, Installation, Testing and Commissioning of E. T. O Machine
View ProjectSupplying and laying of 33 KV underground cable from Sub Station to District Hospital at Mapusa
View Project