Project Duration
Stipulated Date of Commencement
February 20 2014
Stipulated Date of Completion /
Likely Date of Completion August 29 2014
Likely Date of Completion August 29 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,668,077.00
Awarded for
₹ 7,177,614.00
Project highlights
Reconstruction of Primary School with G+1 Structure.
Contractors
M/s. Trivikram Constructions
Consultants
M/s. Bhaskar Wagle and Associates
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil, Plumbing & Electrical works in Bicholim Taluka – Package F (G.P.S. Kelbaiwada Mayem, G.P.S. Borde, G.P.S. Bhavkai Mayem, G.P.S. Haldonwadi Mayem ).
View Project
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil,Plumbing & Electrical works-Package J – Sattari Taluka – GPS Kumbharkand, GPS Tamitgi, GPS Kesarkarwada, GPS Bagwada
View Project
Repairs/ Upgradation & Maintenance of Government Primary schools in the State of Goa –Civil, Plumbing & Electrical works (Bardez Taluka) Package I-C:- GPS Sirsaim, GPS Coniwada, GPS Tarawada
View Project