Project Duration
Stipulated Date of Commencement
February 27 2015
Stipulated Date of Completion /
Likely Date of Completion April 26 2015
Likely Date of Completion April 26 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,323,598.00
Awarded for
₹ 6,353,797.50
Contractors
M/s. Amardeep Designers India Pvt. Ltd.
Consultants
M/s. Datta Kare Associates