Project Duration
Stipulated Date of Commencement
May 28 2016
Stipulated Date of Completion /
Likely Date of Completion August 27 2017
Likely Date of Completion August 27 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,093,176.00
Awarded for
₹ 13,663,217.60
Project highlights
On Ground Floor, the Building conssists of 4 shops of area 12m2 – Post Office, Electricity Room , Gym, Library and Toilet Block.
Contractors
M/s.Vaishnavi Infrastructure
Consultants
M/s. Nitin Arolkar