Project Duration
Stipulated Date of Commencement
February 26 2004
Stipulated Date of Completion /
Likely Date of Completion August 25 2004
Likely Date of Completion August 25 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,611,394.00
Awarded for
₹ 14,350,277.00
Project highlights
• First four lane bridge in Goa.
• The bridge serves as an important link joining the southern part of Goa to the Margao city.
• Length : 18.6 m, width : 19 m including footpaths.
• Length of approaches : 100 m, width : 19 m with adequate lighting and proper drainage system.
Contractors
M/s. Laxmi Civil Engg. Services Pvt. Ltd.
Consultants
M/s. Keni & D’Souza
See Similar Projects
Construction of bridge at Paikul, Sattari-Goa
View Project
Demolition & Salvaging of existing jetty at Kala Academy.
View Project
Conversion of Overhead Lines to underground system and installation of 11KV & LT equipment’s along the road from NIO circle to Dona Paula Jetty and NIO circle to Rajbhavan road
View Project