Project Duration
Stipulated Date of Commencement
November 14 2017
Stipulated Date of Completion /
Likely Date of Completion December 14 2017
Likely Date of Completion December 14 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,019,832.00
Awarded for
₹ 8,371,107.76
Project highlights
Painting of buildings for IFFI 2017
Contractors
M/s.Rakesh Kambli
Consultants
M/s.Vaishali Pednekar & Associates