Project Duration
Stipulated Date of Commencement
January 14 2022
Actual Date of Completion
May 12 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,695,125.00
Awarded for
₹ 2072768.94
Final Cost of Project
₹ 2,588,721.00
Project highlights
Roofing works at Community Health Centre, Canacona
Contractors
M/s Aditya P. Kamat Tarcar
Consultants
In house