Project Duration
Stipulated Date of Commencement
June 08 2018
Stipulated Date of Completion /
Likely Date of Completion April 17 2019
Likely Date of Completion April 17 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,201,277.20
Awarded for
₹ 20,032,911.00
Project highlights
Repair and upgrade the existing structure by maintaining the original aesthetics (old age Portuguese Structure) with lot of problems like roof leakages, wall cracks and uneven plaster surfaces, wall dampness, leakages in toilet etc The upgraded structure will house the following facilities-3 Dormitaries on GF,altar room, visitors room/ office on FF, kitchen, dinning, store room, fire wood store room, toilet blocks.
Contractors
M/s. Kumawat Infrastructure Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Refurbishment of Maquinex Palace Annexe and heritage building – Interior works of ESG.
View Project
Construction of Sewage Treatment Plant at Sanquelim, Goa – Connection of houses to sewer lines.
View Project
Theatre System (non-proprietory).
View Project