Project Duration
Stipulated Date of Commencement
May 28 2022
Stipulated Date of Completion /
Likely Date of Completion October 20 2023
Likely Date of Completion October 20 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,319,361.00
Awarded for
₹ 12,684,665.37
Project highlights
Repair of existing IPA Provedoria at chinchinim
Contractors
M/s. A. Y. Gulumkar
Consultants
M/s. FP Project Management