Project Duration
Stipulated Date of Commencement November 23 2017
Actual Date of Completion May 22 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,536,750.00
Awarded for ₹ 1,399,200.00
Final Cost of Project ₹ 1608400

Project highlights

Maintenance of Cold storages in Goa Medical College

 
Contractors
M/s. Vigneshwar Air Conditioning Pvt. Ltd
Consultants
Inhouse
 