Project Duration
Stipulated Date of Commencement January 10 2018
Actual Date of Completion June 05 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 345,101.00
Awarded for ₹ 342,014.00
Final Cost of Project ₹ 423,582.00

Project highlights

SITC of 2 Nos. 5.5TR ductable units for MRI section at Goa Medical College, Bambolim-Goa.

 
Contractors
M/s. Vighneshwar Airconditioning Pvt. Ltd.
Consultants
Inhouse (GSIDC)
 

See Similar Projects

Beautification of lake at Curtorim (Ralloitollem).

View Project

Upgradation of Government college at Pernem Goa – Interior and Furniture works

View Project

Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa : SH – Procurement of additional works/items and medical equipments required for Ward No.125 and Cardiovascular Surgical Operation Theatre- Supply, Installation and Testing and Commissioning of Xenon Headlight