Project Duration
Stipulated Date of Commencement
March 21 2018
Stipulated Date of Completion /
Likely Date of Completion March 20 2021
Likely Date of Completion March 20 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 860,600.00
Awarded for
₹ 860,600.00
Project highlights
Maintenance work
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Consultants
In-house (GSIDC)