Project Duration
Stipulated Date of Commencement August 30 2004
Actual Date of Completion December 26 2004
Status
100%
Completed
Cost (₹)
Estimated at ₹ 19,938,000.00
Awarded for ₹ 20,933,000.00
Final Cost of Project ₹ 26,736,164.00

Project highlights

? Hard landscaping like compound wall, paved plazas, semi-paved decks, spaces, kerbs, parking areas, café sitouts, planter boxes, etc.
? Soft landscaping like lawns, vases, trees, specimen plants, shrubs, rockery, pebbles and also includes services like stormwater drainage, external electrical works, landscape plumbing and street furniture.

 
Contractors
M/s. R. B. S. Candiaparcar, M/s. R. B. S. Candiaparcar
Consultants
M/s. Prabhugaonker & Associates, M/s. Prabhugaonker & Associates
 

See Similar Projects

Additional Air Conditioning additions/ Alterations to the office building of Directorate of Education at Porvorim, Goa.

View Project

Beautification of lake at Curtorim (Ralloitollem).

View Project

Minor Maintenance / Renovation works at Hospitals, Health Centres and Institutions under Directorate of Health Services, in the State of Goa – Exterior and Interior painting works

View Project
x