Project Duration
Stipulated Date of Commencement
April 30 2012
Stipulated Date of Completion /
Likely Date of Completion October 29 2012
Likely Date of Completion October 29 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 52,151,492.00
Awarded for
₹ 4,98,51,017.15
Project highlights
Interior Works for Ravindra Bhavan at Baina.
Contractors
M/s. T. S. Mistry
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.