Project Duration
Stipulated Date of Commencement September 14 2010
Stipulated Date of Completion /
Likely Date of Completion
November 23 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 24,341,483.24
Awarded for ₹ 18,900,000.00
 