Project Duration
Stipulated Date of Commencement September 14 2010
Stipulated Date of Completion /
Likely Date of Completion
November 23 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 24,341,483.24
Awarded for ₹ 18,900,000.00
 
Gallery Image
Contractors
M/s. Knchan Associates
Gallery Image
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

False ceiling work.

View Project
Similar Project

Power Supply.

View Project
Similar Project

Supply, Installation, Testing and Commissioning of ACT machine

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.