Project Duration
Stipulated Date of Commencement July 31 2015
Actual Date of Completion February 29 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,627,884.00
Awarded for ₹ 5,477,777.00
Final Cost of Project ₹ 5,195,289.00

Project highlights

Interior work for TCP branch office

 
Contractors
M/s. Harshada Trading co.
Consultants
M/s. Intrinsic Classic
 

See Similar Projects

Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa : SH – Procurement of additional works/items and medical equipments required for Ward No.125 and Cardiovascular Surgical Operation Theatre- Supply, Installation and Testing and Commissioning of Xenon Headlight

View Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Maintenance of 200 KVA transformer installed at Primary Health Centre, Pillem Dharbandora (PHC Tisk

View Project

Supply, erection and commissioning of Diesel Generator Sets

View Project
x