Project Duration
Stipulated Date of Commencement August 30 2018
Stipulated Date of Completion /
Likely Date of Completion
September 08 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 170,155,916.00
Awarded for ₹ 174,845,805.00

Project highlights

Interior & furniture works

 
Gallery Image
Contractors
M/s. Jayant K. Furnishers
Gallery Image
Consultants
M/s. Rajesh Kenkre
 
Similar Projects

See Similar Projects

Similar Project

Construction of Sanskruti Bhavan for Department of Tribal Welfare in Canacona Taluka at Adarshgrem, Ammonae-Poinguinim,Gaondongrem, Kulgati,Edda & Guleli

View Project
Similar Project

Internal, external and special lighting fixtures (Part A – Supply of internal light fixtures / fans)

View Project
Similar Project

Landscaping and Horticulture works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.