Project Duration
Stipulated Date of Commencement
January 30 2014
Stipulated Date of Completion /
Likely Date of Completion February 13 2014
Likely Date of Completion February 13 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 49,979,192.00
Awarded for
₹ 47,708,350.00
Project highlights
Hotmixing of road from District collectorate upto Agalli junction, Fatorda
Contractors
M/s.Ritesh Developers Pvt. Ltd
Consultants
M/s.Datta Kare Associates
See Similar Projects
Dismantling of HT overhead lines, supplying & laying of HT underground cables at Panaji – Cable work from Kadamba substation to Chimbel junction.
View Project
Construction of Bus Stand & Mini Depot at Sankhali, Goa. – Balance works
View Project
Construction of Bus Stand at Shiroda – Phase II : Civil works, internal electrification and road
View Project





