Project Duration
Start Date 12/29/2016
End Date 11/30/2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,888,675.00
Awarded for ₹ 3,791,615.00
Final Cost of Project ₹ 4,270,321.00
 