Project Duration
Stipulated Date of Commencement
December 29 2016
Stipulated Date of Completion /
Likely Date of Completion March 28 2017
Likely Date of Completion March 28 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,888,675.00
Awarded for
₹ 3,791,615.00
Project highlights
External Lighting Work
Contractors
M/s.James Electricals
Consultants
M/s. Vijaykumar Sawant Associates