Project Duration
Stipulated Date of Commencement December 29 2016
Stipulated Date of Completion /
Likely Date of Completion
March 28 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,888,675.00
Awarded for ₹ 3,791,615.00

Project highlights

External Lighting Work

 
Gallery Image
Contractors
M/s.James Electricals
Gallery Image
Consultants
M/s. Vijaykumar Sawant Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of subway at Bambolim – Civil works

View Project
Similar Project

Maintenance works of Goa Medical College and Hospital & Goa Dental College at Bambolim, Goa. SH – Carriage of water”

View Project
Similar Project

HVAC Works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.