Project Duration
Stipulated Date of Commencement
March 08 2019
Stipulated Date of Completion /
Likely Date of Completion June 07 2019
Likely Date of Completion June 07 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 18,195,717.00
Awarded for
₹ 20,317,614.73
Project highlights
Furniture and Interior Works
Contractors
M/s. Decor Home (India) Pvt. Ltd.
Consultants
M/s Vijaykumar Sawant Associates.,