Project Duration
Stipulated Date of Commencement November 09 2018
Stipulated Date of Completion /
Likely Date of Completion
March 08 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 22,119,472.00
Awarded for ₹ 17,220,494.00

Project highlights

Providing furniture and interior works at RMO Hostel at GMC.

 
Gallery Image
Contractors
M/s.Virender Kumar & Co.
Gallery Image
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Rural Medical Dispensary at Thane

View Project
Similar Project

Site development and hard landscaping of area around OPD, Casualty, Ward block and Courtyards at GMC, Bambolim, Goa.

View Project
Similar Project

External electrical work

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.