Project Duration
Stipulated Date of Commencement
December 18 2009
Stipulated Date of Completion /
Likely Date of Completion February 17 2011
Likely Date of Completion February 17 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,376,099.00
Awarded for
₹ 8,679,690.00
Project highlights
Construction of additional 4 classrooms, laboratory, compound wall, store room, hall along with painting and electrification works.
Contractors
M/s. K. G. Thomas
Consultants
M/s. Effective Architectural Services