Project Duration
Stipulated Date of Commencement
February 28 2014
Stipulated Date of Completion /
Likely Date of Completion February 27 2015
Likely Date of Completion February 27 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 92,020,305.00
Awarded for
₹ 110,973,898.96
Project highlights
This is an examination hall with auditorium of capacity of 250 students
Contractors
M/s. Indage Development Construction Pvt. Ltd.
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD