Project Duration
Stipulated Date of Commencement
April 07 2017
Stipulated Date of Completion /
Likely Date of Completion October 13 2017
Likely Date of Completion October 13 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 18,878,576.00
Awarded for
₹ 20,699,311.00
Project highlights
The project is having fully ventilated processing unit, office, security room, truck cleaning bay, leached tank, weighbridge facility etc. All internal road and processing area is made of concrete (VDF Floor).
Contractors
M/s.Rakesh Kambli
Consultants
M/s.Rahul Deshpande (Pre-tender)/ M/s.Manoj Amshekar (PMC)