Project Duration
Stipulated Date of Commencement October 28 2014
Stipulated Date of Completion /
Likely Date of Completion
November 27 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 45,817,308.00
Awarded for ₹ 49,506,270.40

Project highlights

Conversion of electrical overhead lines to underground cables.

 
Gallery Image
Contractors
M/s. Nanu Engineers Pvt. Ltd.,
Gallery Image
Consultants
M/s. Nitin Arolkar
 
Similar Projects

See Similar Projects

Similar Project

Laying of paver blocks on Promenade/ Footpath along D. B. Marg in Panaji.

View Project
Similar Project

Construction of Bridge across Rua de Ourem Creek, Panaji – Shifting of 11 KV Cable

View Project
Similar Project

Construction of Minor Bridge across river Tar at Mapusa, Goa on MDR-14

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.