Project Duration
Stipulated Date of Commencement
January 26 2019
Stipulated Date of Completion /
Likely Date of Completion August 31 2024
Likely Date of Completion August 31 2024
Status
85%
Completed
Cost (₹)
Estimated at
₹ 140,801,898.00
Awarded for
₹ 144,773,553.70
Project highlights
Master planning involving construction of concrete road, foothpath, landscaping, electrification and street furniture
Contractors
M/s. Michael & Michael Pipes Pvt. Ltd
Consultants
M/s. Rahul Deshpande & Associates
See Similar Projects
Construction of Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka – Balance RMU Works & Shed work for existing 11 KV 315 KVA Transformer Substation.
View Project
Construction of Multipurpose Hall having Badminton Court, Gymnasium, Changing Room and Other facilities at Socorro Ground, Goa – Civil, Plumbing, Electrical, Lift, HVAC and Fire Fighting Works – Balance Works
View Project
Reconstruction of Government Primary School at Bhoma, Ponda Goa – Civil, Plumbing & Electrical works
View Project