Project Duration
Stipulated Date of Commencement
January 10 2014
Stipulated Date of Completion /
Likely Date of Completion March 22 2014
Likely Date of Completion March 22 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 406,169.00
Awarded for
₹ 398,750.00
Contractors
M/s. Delta Technologies
Consultants
In-house (GSIDC)