Project Duration
Stipulated Date of Commencement
January 23 2006
Actual Date of Completion
September 30 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,700,000.00
Awarded for
₹ 25,218,510.00
Final Cost of Project
₹ 24,504,844.00
Contractors
M/s. Schindler (I) Pvt. Ltd., M/s. Schindler (I) Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd